A facility installed and operated to be provided for performances for 90 days or more a year or for 30 consecutive days or more is a performance venue under the Public Performance Act, and anyone who wants to operate one must meet the facility standards and register with the city, county or district where it is located (Public Performance Act, Article 9; Enforcement Decree, Article 1-2). The facility standards are stage facilities (including lighting and sound) and soundproofing facilities, and before registration the venue must pass a safety inspection by a designated stage facility safety diagnosis agency, whose result is attached to the application. The processing period for the registration application is 7 days; the disaster response plan for the current year is reported together with the registration application, and after that the plan for the following year is reported by December 31 every year.
Procedure
1. Check whether registration is required and the building use
A performance means showing artistic works such as music, dance, theater, musicals, entertainment, Korean traditional music and acrobatics to the public by live performance, and performances that accompany product sales or advertising are excluded. A facility to be provided for such performances for 90 days or more a year or for 30 consecutive days or more must be registered. If the total floor area used as a performance venue in the same building is less than 500㎡, the building use must be Class II neighborhood living facility, and otherwise cultural and assembly facility, so check the use and any illegal building mark in the building register before signing the lease.
2. Prepare the facility standards and the stage facility safety inspection
The facilities required for registration are stage facilities including lighting and sound, and soundproofing facilities, and a venue with no ceiling over the seating area may omit soundproofing. If the stage machinery and equipment driven independently above and below the stage total 40 or more, a design review is required before construction starts, and every venue must pass a pre-registration safety inspection by a stage facility safety diagnosis agency. A venue with 1,000 seats or more must install a fire curtain on the stage unless it has been recognized as exempt by the Minister of Culture, Sports and Tourism.
3. Prepare the disaster response plan
The disaster response plan must include all of the following: the duties and management organization of the persons who manage the venue facilities, prevention of crowd crush accidents, safety management when installing and dismantling stage facilities, emergency measures and contacts, fire prevention and casualty prevention measures, and matters on safety management costs, the safety management organization, safety training and evacuation guidance. A venue with 500 seats or more must allocate at least 1% of its venue operating costs as safety management costs and appoint a chief safety officer and a safety manager. The venue must keep an evacuation map showing evacuation stairs, passages and equipment, or explain evacuation procedures to the audience before the performance starts.
4. Submit the registration application and receive the registration certificate
Submit the performance venue registration application (Enforcement Rule of the Public Performance Act, Form No. 10) to the city, county or district office with the facility installation statement, floor plan and layout plan, documents proving ownership or right to use the property, and the design review result (if applicable) and pre-registration safety inspection result from the safety diagnosis agency. Together with the registration application, report the disaster response plan for the current year using Form No. 13-3. The processing period is 7 days, the fee is set by city, county or district ordinance, and a performance venue registration certificate is issued unless the facility standards or safety inspection standards are not met or another statutory restriction is breached.
5. Manage change registrations and periodic inspections after registration
If the operator, venue name, stage machinery and equipment, number of seats, stage area or seating floor area changes, file a change registration (processing period 3 days), and if the business is closed, file a closure report within 30 days. The periodic safety inspection of stage facilities must be taken within 31 days before or after the date on which 3 years have passed since registration or the last inspection, and the precise safety diagnosis within 31 days before or after the date on which 9 years have passed; a self safety inspection must be carried out every year and its results kept for 3 years. The disaster response plan for the following year must be reported by December 31 every year, and any change must be reported before it is applied.
Required documents
- Performance venue registration (change registration) application (Enforcement Rule of the Public Performance Act, Form No. 10)
- Facility installation statement (divided into stage overview, seating, lobby, dressing rooms, stage machinery, lighting, sound and video)
- Floor plan and layout plan of the facility
- Documents proving ownership of or the right to use the property (lease agreement, etc.)
- Design review result (only for venues subject to it) and pre-registration safety inspection result from the stage facility safety diagnosis agency
- Performance venue disaster response plan report (Enforcement Rule of the Public Performance Act, Form No. 13-3)
- Electrical safety inspection confirmation (if you do not consent to administrative information sharing)
- Letter of authorization (when an administrative agent submits on your behalf)
Fees
Industry range of several hundred thousand won · We provide a quote after consultation based on the number of seats, the length of the disaster response plan, and whether a safety management organization is required. Inspection costs of the safety diagnosis agency, facility construction costs and the registration fee are separate.
Legal basis and review date
- Public Performance Act, Article 2
- Public Performance Act, Article 8
- Public Performance Act, Article 9
- Public Performance Act, Article 11
- Public Performance Act, Article 11-2
- Public Performance Act, Article 11-3
- Public Performance Act, Article 11-5
- Public Performance Act, Article 11-7
- Public Performance Act, Article 12
- Public Performance Act, Article 16
- Public Performance Act, Article 43
- Enforcement Decree of the Public Performance Act, Article 1-2
- Enforcement Decree of the Public Performance Act, Article 8
- Enforcement Decree of the Public Performance Act, Article 9
- Enforcement Decree of the Public Performance Act, Article 9-2
- Enforcement Decree of the Public Performance Act, Article 9-3
- Enforcement Decree of the Public Performance Act, Article 9-7
- Enforcement Decree of the Public Performance Act, Article 10
- Enforcement Decree of the Public Performance Act, Article 21
- Enforcement Decree of the Public Performance Act, Annex 1-2
- Enforcement Decree of the Public Performance Act, Annex 3
- Enforcement Decree of the Public Performance Act, Annex 4
- Enforcement Rule of the Public Performance Act, Article 5
- Enforcement Rule of the Public Performance Act, Article 6
- Enforcement Rule of the Public Performance Act, Form No. 10
- Enforcement Rule of the Public Performance Act, Form No. 13-3
- Enforcement Decree of the Building Act, Annex 1
Check these first
- If the venue use in the building register (Class II neighborhood living facility or cultural and assembly facility) and any illegal building mark are not checked before signing the lease, registration may be refused for breach of another statutory restriction even after the facilities are installed.
- When holding a performance expected to draw 1,000 or more spectators at a place other than a performance venue, a disaster response plan must be reported jointly with the operator of the place at least 14 days before the performance starts, separately from venue registration.
Frequently asked questions
Do small theaters and live music venues also need performance venue registration?
What happens if I operate a performance venue without registering it?
How long does performance venue registration take?
Does a private small theater have to assign certified stage art professionals?
When is the performance venue disaster response plan reported?
Does an administrative agent handle performance venue registration?
Contact us
Hwang Yunsang Administrative Office in Songdo, Incheon prepares and submits administrative documents and explains the procedure. If your situation is similar, send us a message.
📍 2697, 26F POSCO Tower-Songdo, 165 Convensia-daero, Yeonsu-gu, Incheon, Republic of Korea · 📞 010-3374-2687 · 🌐 hwangadmin.com
This guide is general information based on public sources. Requirements, documents and deadlines differ by case and by the competent agency, so please confirm them before you proceed.